AHK Chamber Membership Directory project

Company: Real Softservice
Manager: Zhang Weiwu
Start: April 1, 2007
Finish: April 30, 2007
Phase: Pilot Period
Report Date: April 10, 2007

Gantt Chart

Week 15, 2007 Week 16, 2007 Week 17, 2007 Week 18, 2007
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30
zww, wos, paul, dxl
dxl
dxl
zww, wbsh
zww
dxl
wbsh
zww, wbsh
zww, wos, dxl
zww, wos, paul

Tasks

WBS Name Start Finish Work Priority Complete Cost Notes
1 Project Planning Meeting Apr 2 Apr 2 4d 100% Meeting in Beijing, Decision about To-Do-List, following tasks tbc
2 Adjust records of companies abused "Business Activities" field Apr 10 Apr 23 10d 20% First RealSS generate a list of company to update (#1541)
3 Check and hide Hong Kong companies and Chamber Members Apr 12 Apr 18 4d 0%
4 Creating and discuss Action Requests Apr 6 Apr 6 1d 100% 3,000
5 Agreement of Project Plan Apr 10 Apr 10
6 Reorganize Categories Apr 10 Apr 12 1d 0%
7 Fill Pilot Data Apr 12 Apr 16 2d 0%
8 Application Development Apr 10 Apr 19 7d 0% 18,480
9 Alpha Test and batch update Apr 19 Apr 19 1d 0% 3,000 Also create accounts for all chamber managers
10 Beta Test Apr 24 Apr 24 2d 1h 0%
11 Introduce the system to AHK Chambers Apr 30 Apr 30

Resources

Name Short name Type Group Email Cost
Du Xiaolin dxl Work Real Softservice du.xiaolin@sh.china.ahk.de 0
Paul Bachmann paul Work Real Softservice bachmann.paul@sh.china.ahk.de 0
Shang Wenbin wbsh Work Real Softservice wbsh@realss.com 375
Wolfgang Scheuing wos Work Real Softservice scheuing@realss.com 0
Zhang Weiwu zww Work Real Softservice zhangweiwu@realss.com 0